First day using it.. Kekekekeke!!!
Anyway, our dear ED sms me last night with a reminder to send the following email. (Which I already did so earlier that evening..) See?! He is so forgetful.
Anyways, I drafted something like this:
What more can I say.. WE ARE DESPERATE.
Dear S---- / Ms T---
Till date, DLX have assessed all of Phase 1 variations, excluding Kxx Lxx and Axx as they have already been allowed for in the Provisional Sums.
We arrived at the sum of $10.5 million vs. GX's $18 million, which includes Kxx Lxx and Axx amounting to almost $5 million. GX's figures (excluding the $5M) should be adjusted to $13M. The variance in cost primarily stemmed from the $2.3M for the structural remeasurement which will be subject to bulk check upon further agreement.
The nett difference [i.e $10.5M (DLX) vs $10.7M (GX)] is considered marginal and we would urge GX to agree with our assessed figure except for the structural remeasurement.
Thanks and Regards
E / Jade